PROJECT REFERENCE – CLUSTER MEGALO MONASTIRI | 43 MWp | Greece
Location: Megalo Monastiri & Mikro Perivolaki
Total Capacity: 43 MWp
Implementation Period: 3 months
The Megalo Monastiri Cluster is a large-scale photovoltaic development consisting of three (3) solar parks, with a total installed capacity of 43 MWp.
Developed in demanding terrain conditions, the project extends across areas with varying elevations and slopes, requiring flexible engineering solutions and precise adaptation to the landscape.
To meet these challenges, multiple mounting table designs were developed and implemented, each one fully customized to the specific requirements of each location.
For every table type, dedicated structural calculations were carried out, ensuring safety, reliability, and long-term structural performance.
Production & Supply Chain
The project execution was supported by 66+ truck deliveries, scheduled with absolute precision in arrival timing, ensuring uninterrupted progress at all construction sites.
Each shipment was delivered with project coding, detailed packing lists, and clearly labeled bundles indicating project and destination.
This methodical approach to packaging, production planning, and logistics ensured perfect coordination between manufacturing, transportation, and on-site installation.
Result
Completed on time and according to plan, the Megalo Monastiri Cluster stands as a strong reference project and a clear demonstration of Profilodomi’s ability to deliver large-scale, high-complexity photovoltaic clusters with reliability, precision, and engineering excellence.